Tuesday, March 5, 2019
Cost Control and Cost Reduction
PRINCIPLES OF COST CONTROL 1. 1 Introduction Cost is important to entirely told industry. Costs kitty be split up into two general classes lordly equals and relative make ups. Absolute address measures the loss in quantify of assets. Relative apostrophize involves a comparison between the chosen quarrel of act and the course of action that was rejected. This live of the substitute(a) action the action not taken is a good deal c bothed the opport unit of measurementy live. The accountant is mainly refer with the absolute woo.However, the forest engineer, the planner, the manager needs to be concerned with the preference woo the terms of the lost opportunity. Management has to be able-bodied to make comparisons between the policy that should be chosen and the policy that should be rejected. Such comparisons require the ability to predict cost, rather than merely drop off costs. Cost data ar, of course, essential to the technique of cost expectancy. However , the form in which much cost data atomic number 18 recorded limits accu site cost prediction to the field of comparable situations summarisely.This limitation of accu put cost prediction may not be serious in industries where the production environment changes little from month to month or year to year. In harvesting, however, indistinguishable production situations atomic number 18 the exception rather than the rule. Unless the cost data are broken down and recorded as unit costs, and correlated with the factors that take hold their values, they are of little use in deciding between alternative procedures. Here, the approach to the problem of useful cost data is that of identification, isolation, and control of the factors affecting cost. . 2 Basic Classification of Costs Costs are divided into two types variable star costs, and ameliorate costs. Variable costs vary per unit of production. For example, they may be the cost per box-shaped meter of wood yarded, per thir d-dimensional meter of dirt excavated, etc. Fixed costs, on the other hand, are incurred only once and as additional units of production are produced, the unit costs fall. Examples of unflinching costs would be equipment move-in costs and highroad find costs. 1. 3 Total Cost and Unit-Cost Formulas As harvesting operations capture more than complicated and involve both(prenominal) fixed and ariable costs, there ordinarily is more than one way to accomplish a given task. It may be possible to change the quantity of one or both types of cost, and thus to arrive at a minimum replete(p) cost. Mathematically, the alliance existing between volume of production and costs can be expressed by the pursual equations Total cost = fixed cost + variable cost ? output In symbols using the first letter of the cost elements and N for the output or number of units of production, these simple formulas are C = F + NV UC = F/N + V 1. Breakeven Analysis A breakeven digest determines the reques t at which one method becomes superior to another(prenominal)(prenominal) method of accomplishing some task or objective. Breakeven analysis is a uncouth and important part of cost control. One illustration of a breakeven analysis would be to compare two methods of road construction for a road that involves a limited amount of cut-and-fill earthwork. It would be possible to do the earthwork by hand or by bulldozer. If the manual method were adopted, the fixed costs would be low or non-existent.Payment would be done on a routine basis and would call for direct supervision by a foreman. The cost would be calculated by estimating the date required and multiplying this metre by the median(a) wages of the men employed. The men could also be paid on a piece-work basis. Alternatively, this work could be done by a bulldozer which would have to be travel in from another site. Let us assume that the cost of the hand labor would be $0. 60 per cubic meter and the bulldozer would cost $0. 4 0 per cubic meter and would require $100 to move in from another site.The move-in cost for the bulldozer is a fixed cost, and is independent of the quantity of the earthwork handled. If the bulldozer is used, no economy will result unless the amount of earthwork is sufficient to carry the fixed cost plus the direct cost of the bulldozer operation. Figure 1. 1 Breakeven Example for Excavation. If, on a set of coordinates, cost in dollars is plan on the vertical axis and units of production on the horizontal axis, we can indicate fixed cost for any process by a horizontal line parallel to the x-axis. If variable ost per unit output is constant, because the come cost for any number of units of production will be the sum of the fixed cost and the variable cost multiplied by the number of units of production, or F + NV. If the cost data for two processes or methods, one of which has a higher variable cost, moreover lower fixed cost than the other are plotted on the same graph, the to tal cost lines will intersect at some point. At this point the levels of production and total cost are the same. This point is known as the breakeven point, since at this level one method is as economical as the other.Referring to Figure 1. 1 the breakeven point at which quantity the bulldozer alternative and the manual labor alternative become equal is at five hundred cubic meters. We could have found this same result algebraically by writing F + NV = F + NV where F and V are the fixed and variable costs for the manual method, and F and V are the corresponding values for the bulldozer method. Since all values are known except N, we can solve for N using the formula N = (F F) / (V V) 1. 5 Minimum Cost Analyses A similar, but different problem is the determination of the point of minimum total cost.Instead of balancing two methods with different fixed and variable costs, the aim is to transmit the sum of two costs to a minimum. We will assume a clearing crew of 20 men is clearing road right-of-way and the following facts are available 1. Men are paid at the rate of $0. 40 per hour. 2. Time is measured from the time of leaving mob to the time of return. 3. Total locomote time per man is increasing at the rate of 15 minutes per day. 4. The cost to move the multitude is $50. If the camping ground is moved each day, no time is lost walk of life, but the camp cost is $50 per day.If the camp is not moved, on the second day 15 crew-minutes are lost or $2. 00. On the third day, the total walking time has increased 30 minutes, the fourth day, 45 minutes, and so on. How often should the camp be moved assuming all other things are equal? We could derive an algebraic expression using the sum of an arithmetic series if we wanted to solve this problem a number of times, but for demonstration purposes we can simply calculate the average total camp cost. The average total camp cost is the sum of the average free-and-easy cost of walking time plus the average daily c ost of travel camp.If we moved camp each day, accordingly average daily cost of walking time would be zero and the cost of moving camp would be $50. 00. If we moved the camp every other day, the cost of walking time is $2. 00 lost the second day, or an average of $1. 00 per day. The average daily cost of moving camp is $50 divided by 2 or $25. 00. The average total camp cost is then $26. 00. If we continued this process for various numbers of days the camp corpse in location, we would obtain the results in Table 1. 1. TABLE 1. 1 add up daily total camp cost as the sum of the cost of walking time plus the cost of moving camp.Days camp remained in location clean daily cost of walking time Average daily cost of moving camp Average total camp cost 1 0. 00 50. 00 50. 00 2 1. 00 25. 00 26. 00 3 2. 00 16. 67 18. 67 4 3. 00 12. 50 15. 50 5 4. 00 10. 00 14. 00 6 5. 00 8. 33 13. 33 7 6. 00 7. 14 13. 14 8 7. 00 6. 25 13. 25 9 8. 00 5. 56 13. 56 10 9. 00 5. 00 14. 00 We see the average dail y cost of walking time increasing linearly and the average cost of moving camp decreasing as the number of days the camp remains in one location increases.The minimum cost is obtained for leaving the camp in location 7 days (Figure 1. 2). This minimum cost point should only be used as a guideline as all other things are rarely equal. An important output of the analysis is the esthesia of the total cost to deviations from the minimum cost point. In this example, the total cost changes slowly between 5 and 10 days. Often, other considerations which may be difficult to quantify will affect the decision. In Section 2, we hash out balancing road costs against skidding costs.Sometimes roads are spaced more closely together than that indicated by the point of minimum total cost if excess road construction capacity is available. In this case the remnant may be to reduce the risk of disrupting skidding production because of poor hold or equipment availability. Alternatively, we may choose to space roads farther asunder to reduce environmental impacts. Due to the usually flat nature of the total cost curve, the increase in total cost is often low-spirited over a wide range of road spacings. Figure 1. 2 Costs for Camp Location Example.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.